Experience in stabilisation of rock slopes in Pahang
Muhammad Hafeez Osman1, Intan Shafika Saiful Bahri2, Damanhuri lamalludin3, Fauziah Ahmad4.
Two cases regarding the histories of rock slopes repair and stabilisation of unstable boulder along Bukit Cincin to Genting Highlands and along the roadfrom Gap to Fraser Hill in Pahang are presented. On 30th October 1997, 10 locations of road failure occurred along the road from Bukit Cincin to
Genting Highland and in December 1997, 33 locations of slope failures occurred along the road from Gap to Fraser Hill during the monsoon seasons. Loose and fractured rocks were removed and covered with polyvinyl chloride (PVC) coated anchored wire netting to prevent rocks fall while rock buttress was used to stabilise unstable boulders in soil slope. The repair works at Location 5 along the road from Bukit Cincin to Genting Highland where highly fractured rock slope and unstable boulder in soil slope occurred and the repair works at Location 10 along the roadfrom Gap to Fraser Hill where highly fractured rock slope occurred are fully discussed in this paper.
Affiliation:
- Universiti Teknologi MARA, Malaysia
- Universiti Teknologi MARA, Malaysia
- Universiti Teknologi MARA, Malaysia
- Universiti Sains Malaysia, Malaysia
Download this article (This article has been downloaded 425 time(s))
|
|
Indexation |
Indexed by |
MyJurnal (2021) |
H-Index
|
2 |
Immediacy Index
|
0.000 |
Rank |
0 |
|
|
|